About the Project
The Town of St. Marys will soon be replacing the Bolton Drain culvert under Queen Street W. Work is scheduled to start the week of November 17. There will be a road closure that will significantly impact commute time for some residents in the area.
Project Scope
Watermain Installation
A watermain needs to be moved out of the way to accommodate the new culvert structure. Watermain installation will occur on the week of November 17. There will be one day the week of November 24 where drinking water needs to be turned off to accommodate the connection of the new watermain pipe. Further details will be delivered by the Town’s operating authority to those affected.
Road Closure/Detour
A full road closure will start Monday November 24 for an anticipated duration of 2.5 weeks. The Town expects to open the road on Wednesday December 10. During that time, residents will need to drive out to Rannoch and then back in around Line 10/Line 14 to James St. N. The road closure is inconvenient but necessary to ensure a relatively quick construction schedule before winter.
Temporary lane closures either before or after the full road closure may be implemented from time to time to accommodate specific work adjacent to the road.
Installation of Temporary Asphalt
Temporary asphalt will be installed to get us through the winter. Final restoration including concrete and asphalt will be completed in the spring of 2026.
Updates:
- Week of Nov 17: Watermain relocation
- Week of Nov 24: Drinking water will be turned off (for one day), Road closure will start (approx. 2.5 weeks)