Skip to main content Skip to footer

Road Closures and Construction

The following is a list of upcoming and ongoing construction projects and road closures.

To apply for a road closure or right of way occupancy request, please see Applications, Licenses and Permits.

To receive regular updates on upcoming and ongoing construction projects, subscribe to receive email notifications. Make sure to select the "Road Closures" category.

For up-to-date information on road closures and disruptions, please visit the Municipal 511 website.

Construction Projects

Project updates

The remaining top coat of asphalt will be installed in the future. 

About the project

Procurement: Tendered

Contractor: COPE Construction & Contracting Inc.

Cost: $1.9 million

Map of construction area

The Town has assessed the Egan Ave. reconstruction project against the current provincial legislation and determined that the project will proceed at this time.

The contractor has a policy for employees and subcontractors working during the pandemic and have enhanced measures in place following healthcare guidelines to reduce the risk of potential transmission of COVID-19 at the project site. Measures include but are not limited to:

  • Physical distancing
  • Personal protective equipment
  • Hand washing stations on site

The Town will be reviewing the project regularly with the contractor to ensure the safety measures are adhered to.

While interacting with workers, please maintain a 2m (6 ft.) distance.

Project components

The project will include:

  • Watermain replacement
  • Storm sewer replacement
  • Sanitary sewer extension
  • Sidewalk replacements and improvements
  • Curb and gutter installation
  • Asphalt road replacement
  • Peel Street and Egan Ave. intersection improvement

About the Project

The Town of St. Marys is scheduled to reconstruct four blocks of Elgin St. E in the summer of 2025, from Wellington St. S to James St. S with ASG Excavating Inc. from Strathroy.

Project Scope

Underground Infrastructure

Underground work will include:

  • installing a new storm sewer from Church St. S to Wellington St. S
  • replacing water service from the water main to property lines
  • making isolated repairs to the sanitary sewer

Above Ground Infrastructure

The project will involve:

  • replacing concrete curbs
  • replacing the road base
  • replacing asphalt
  • replacing sidewalks that have deteriorated

Work Schedule

The project is expected to take 15 weeks and finish by September 2025, with topcoat asphalted paved in 2026. 

Once the schedule is prepared and confirmed, project timeline details will be posted on this webpage. You can subscribe to receive email updates by clicking the 'Receive email updates' button at the bottom of the page.

Important information: Paving will typically start at 7:00 a.m. and residents are asked to move vehicles out of driveways before tack coat is installed.  Tack coat will be applied to the road to ensure a good bond between the existing asphalt and new asphalt. This material will stick to cars and tires and track into driveways, so residents asked not to drive through it. Asphalt can be driven on once the paving crew has moved on. Residents are asked to not park on the new asphalt for a couple days following paving. If a road is closed and a resident needs to get into their driveway, speak to a construction worker and accommodations will be made if possible. 

Wednesday (August 27): Egan Ave

Friday (August 29): St. John St.N, St. George St. N

Tuesday/Wednesday (September 2-3): Thames Rd. N., Widder St. E,

Thursday/Friday (September 4-5): Thomas St., Park Lane, Thames Ave, Charles St., Jones St., Brock St., Glass St. paving

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.